This document reports the results of SCS testing performed during the PFM1 test campaign
at the CSL (Centre Spatial de Liège) facilities. Both SCS TMU’s were integrated on the S/C
but only the unit indicated by SCS-R, officially considered the Redundant one of the two
delivered by JPL, was tested. Ground testing of the Nominal unit, FM2, will be carried out in
the next PFM2 test campaign.
The test campaign spread over about 2 months, from February to March 2006. The SCS was
first activated at the end of February for a warm healthcheck in order to check its functionality
after shipping and then it was switched on again on March 18th 2006 for the actual cryogenic
test: after a thermal vacuum healthcheck, the cooler was started and tested in all cases
according to the test plan.
This report covers tests, results and issues related to the SCS only.
Volume
PL-LFI-PST-RP-016
Rights
open.access
File(s)![Thumbnail Image]()
Loading...
Name
PST-RP-016_1_0_FM1_TestReport_2006.pdf
Size
1.08 MB
Format
Adobe PDF
Checksum (MD5)
1ab7ac1b4e7467cfb23ece83988188db